Channel (including pipes and valves) re-done and outlet structure completed- Aug 27 & 28

Work required to correct the elevation issue caused by the old outlet structure was completed.

The outlet channel is fitted for the beehive grate to be added

The outlet channel is fitted for the beehive grate to be added

Concrete blocks and some cement are used to top-off the outlet structure

Concrete blocks and some cement are used to top-off the outlet structure

Pipes and valves are all back in place

Pipes and valves are all back in place

Mike (TNCC) taking a look – outlet channel to pond complete

Mike (TNCC) taking a look – outlet channel to pond complete

Emergency overflow pipes added back to the channel

Emergency overflow pipes added back to the channel

Mike and Jim (TNCC) discussing next restoration tasks

Mike and Jim (TNCC) discussing next restoration tasks

The ECT and Anglin team deserve a nice weekend – a very long week but a job well done. Yes that’s my buddy out there still eating away!!

The ECT and Anglin team deserve a nice weekend – a very long week but a job well done. Yes…… that’s my buddy out there still eating away!!

.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s